Manage budget
Introduction
A budget's line is defined by:
Entity
Project
Level: Management or Training or Software or Operation or Support or Other
Phase (Pre-Project or Start or Preparing or Work or Closing)
Description
Its values are:
Date
Quote
Founding
Actual cost
Done Task (%)
Foreseen Task (%)
Indicators
Cost Variation (CV)
It is the variation between the done value and the actual cost.
Done Value = Done % * Quote
Cost Variation = Done Value - Actual Cost
Cost Performance Index (CPI)
It is the index between the done value and the actual cost.
Cost Performance Index = Done Value / Actual cost
Schedule Variation (SV)
It is the variation between the done value and the foreseen value.
Foreseen Value = Foreseen % * Quote
Schedule Variation = Done Value - Foreseen Value
Schedule Performance Index (SPI)
It is the index between the done value and the foreseen value.
Cost performance Index = Done Value / Foreseen Value %
Consolidation
This indicators and values could be consolidated by Entity, Project, Level, Phase.
Each budget's line should be historally recorded to get derive trends.